project on software process improvement
      #649856 - 11/23/10 09:57 PM

We are using X, MR Chart for software process improvement for the build phase of the project
I need to do a project to demonstrate how Company without LEVEL 3 looks & then CMMI LEVEL 3 looks & what is the improvement. The same has to be doen for level 5 as well
I ahev to show the charts & data
Also i have to demonstrate using data how the productivity improved & cost reduced for many projects aty Org level
I need some one to guide me in this area
Can some one help me
I have the necessary data
Its about how i can put things together & prove

I dont have data considering many projects at Org Level

My email id is [Email Address Removed by Moderator] Can some on help me
& guide me

Edited by blueinatl (12/09/10 10:37 AM)


Post Extras: Print Post   Remind Me!   Notify Moderator  
SudNay
Newbie


Reged: 08/19/08
Posts: 12
Loc: India
Re: project on software process improvement [Re: spienthu]
      #650880 - 12/02/10 04:20 AM

Spienthu,

I am not sure my reply would help you much. Good to know that you already have required data. First of all the focus on key check points of the two diff levels of CMMi and then once you have the differences b/w the two, gather the required data w.r.t differences and feed in the tool ( any not sure how the tool will differniate). May be you can project With CMMi L3 and Without CMMi L3. The important thing here to remeber is clsoing on the differnces WITH and WITHOUT CMMi L3.

Rgds,
QC


Post Extras: Print Post   Remind Me!   Notify Moderator  
spienthu
Newbie


Reged: 11/23/10
Posts: 4
Re: project on software process improvement [Re: SudNay]
      #652298 - 12/12/10 08:10 PM

thanks a lot for your suggestion Am sorry for the late reply
I will keep posting in this forum for more help
At this point i would also like to know where i will be able to find industry average for the following:
Schedule variance
Effort variance
Pre-delivery defect density
Post-delivery defect density
AVERAGE Productivity in COBOL


Post Extras: Print Post   Remind Me!   Notify Moderator  
FakeSoftwareTester
Member


Reged: 06/29/10
Posts: 51
Re: project on software process improvement [Re: spienthu]
      #652310 - 12/12/10 11:15 PM

Each organization have their own levels for tracking schedule, effort, post delivery and pre-delivery defect density, etc.

That means that most of them are not willing to share actualys, which means there's no industry average available for these.

The best way to find it is to track these values for your company's previous projects and try to calculate if your current project's value is lesser than or greater than those numbers.

--------------------
- Fake Software Tester
(Not a secret identity, but a chosen mask!!!)

http://fakesoftwaretester.blogspot.com


Post Extras: Print Post   Remind Me!   Notify Moderator  
Pages: 1



Extra information
0 registered and 5 anonymous users are browsing this forum.

Moderator:  blueinatl, AJ, Daniel_S, michaeljf, swt88 

Print Topic

Forum Permissions
      You cannot start new topics
      You cannot reply to topics
      HTML is disabled
      UBBCode is enabled

Rating:
Topic views: 4157

Rate this topic

Jump to

Contact Us | Privacy statement SQAForums

Powered by UBB.threads™ 6.5.5