I know this post is old, but I wanted to comment for future reference.
At my previous employer (gaming company), as a QA Director, the company was very new to Scrum and it took several months to addapt and setup a process that most people were happy with. After some research and attempts, this is what worked the best.

- QA team is structured as normal. Director/Manager, Lead(s), and testers.
- Defects/Bugs are prioritized, converted into user stories and added to the main backlog.
- QA Director or PM is responsible for assigning the "new tasks" to the respective team under the current sprint (spring # = priority).