Our company is using HP Quality Center 9.2 on a Windows 2003 server and our systems administrators are preparing to migrate our data off of one Oracle 9i server to two load balanced Oracle 10g servers. My questions is this---the servers are identical and are load balanced, but should I configure both servers on the DB Servers tab from Quality Center Site Administration, or should I just setup one server for each project to link to? Does QC itself do any load balancing, or is this done at the server level?

Thank you for your assistance.